It will take maybe two weeks to repair a observe concern inflicting trains to crawl at pedestrian speeds alongside the Green Line Extension.
MBTA General Manager Phil Eng, throughout a gathering of the transportation company’s board of administrators Tuesday morning, stated a discrepancy within the width of Green Line tracks could possibly be fastened as quickly as mid-November.
“It’s not months, it’s not years to address this,” Eng informed the Board.
Last week, Eng revealed that earlier MBTA officers found however didn’t publicly disclose an issue with the road’s prefabricated railroad ties, resulting in tracks that had been out of design specs and to not nationwide rail requirements.
“We did a deeper dive into the project to understand why a project that was recently opened, new construction, resulted in conditions that were unacceptable,” he stated. “What we identified was that we had tight gauges across significant portions of the GLX project.”
According to Eng, about half of the observe alongside the Union department of the Green Line Extension and 80% of the Medford-Tufts department are outdoors of the business rail gauge commonplace — typically known as the Stephenson gauge — of 56-and-a-half inches. Parts of the observe are between an eighth and a three-eighths of an inch too slim, Eng stated, regardless of the contract calling for not more than a sixteenth of an inch tolerance.
“That does not mean it was unsafe to run trains,” the GM stated.
Under a proposed corrective motion plan supplied by the development conglomerate that put in the tracks, GLX Constructors, work might start as quickly as subsequent month and would happen in a single day, from 9 p.m. to five a.m.
Eng stated the corporate’s proposal, which MBTA officers are nonetheless reviewing, requires “10 to 14 nights of work” beginning on November 1 to “address and regauge all of the track that needs to be done along both branches.”
To repair the issue, Eng informed the board, the pre-installed plates connecting the steel prepare observe to the picket rail ties will must be unbolted, the bolt holes stuffed and re-drilled, and the plates and observe reconnected. The process shouldn’t be solely unusual within the rail business, Eng stated, and his workers is targeted on ensuring the answer gained’t lead to future frustrations.
GLX Constructors — an entity made up of Fluor Enterprises Inc., The Middlesex Corporation, Herzog Contracting Corp. and Balfour Beatty Infrastructure, Inc. — must foot the invoice for fixing the observe downside, in accordance with the GM.
The roughly $2.3 billion Green Line Extension undertaking was accomplished on the finish of final 12 months, with a brand new department that begins in Medford on the Tufts/College Avenue station and provides 4 stops in Somerville. A smaller department opened in March 2022, including service on the Union Square station in Somerville.
The downside with the tracks was apparently found as quickly as April of 2021 — effectively earlier than the ribbon reducing ceremonies — however by no means addressed. The board didn’t appear stunned when Eng informed them the time to repair the issue was upon identification, not after service started. The slim tracks have resulted in trains that transfer as sluggish as 3 mph at instances, or in regards to the common strolling pace for many wholesome adults.